Highlights from the Q3 2014 Pipeline Report by the SF Planning Department
December 2014, compiled by Paragon Real Estate Group
On December 19th, the San Francisco Planning Department issued its excellent Q3 2014 Pipeline Report, which tracks new residential and commercial development in the city. There is a wealth of data within its 36 pages: Below is simply an excerpt of some highlights.
The Pipeline includes projects in every stage of the approvals, permits and construction process, and being listed in the pipeline doesn’t indicate when or even if the project will be completed. Changes and additions to the pipeline occur on an ongoing basis: Indeed, it seems rarely a day goes by nowadays without a big new project being announced. Last but not least, changes in economic and political circumstances can suddenly and dramatically impact new development plans and construction.
- 50,600 residential units are in the current pipeline, including condos, houses and apartments, as well as affordable and social-project housing. Houses constitute far less than 1% of the total units. (There are currently approximately 381,000 housing units in San Francisco, per 2013 U.S. Census data.)
- 18,700,000 square feet of commercial space are in the pipeline, including office, retail, medical, hotel, cultural, institutional and educational uses. 12 million of the square footage in the pipeline are for office use. (As of 2013, there were approximately 75.6 million square feet of office space in the city.)
- 3090 residential units and 280,000 square feet of commercial space have been added in the past 4 quarters. “The median time to completion for these projects from the first filing was 43 months.” For smaller projects of less than 10,000 square feet, the median time dropped to 30 months.
- 6700 new residential units and 5,400,000 square feet of commercial space are currently under construction.
- Approximately 25,800 of the pipeline’s residential units are comprised of the Bayview/Hunter’s Point/Candlestick, Park Merced and Treasure Island projects. “Full realization of the projects will be decades into the future.” The Bayview/Candlestick and Treasure Island developments are situated on parcels designated as “Public Land.”
- Not counting the 3 big projects mentioned above, the great majority of both residential and commercial pipeline projects are currently clustered in the greater South Beach/South of Market/Mission Bay area, the Market Street corridor, the Potrero Hill/Dogpatch area, and the Mission.
- Approximately 800,000 square feet of manufacturing, distribution and repair use space would be lost in the course of existing pipeline development, to be replaced by housing or other commercial uses.
The full Planning Department Pipeline Report can be downloaded here. There’s also a nifty interactive map illustrating projects in the pipeline. Our sincere gratitude to Aksel Olsen and Teresa Ojeda of the SF Planning Department for compiling this useful and comprehensive report.



This snapshot from the interactive map on the Planning Department’s Pipeline report webpage indicates current projects in the greater South Beach/South of Market/Mission Bay district, Hayes Valley and the Market Street corridor.